2025-2026

Eastside Classroom

Expansion Progress update


In collaboration with Weaver Commercial Contractors, the Eastside Classroom Expansion Project began in June 2025. This building project is designed to add four new classrooms through the following phases by July 2026. However, we must raise the remaining estimated funds as indicated below. Any funds we receive beyond our construction costs will be used towards furnishing the new classrooms.

Funding Update

as of October 14, 2025

Phase 1 -  Sitework

100%

Fully Funded!

Original Estimate $300,000

Funding Needed $0

Phase 2 - Exterior Structure

79%

Funds Raised

Original Estimate $415,000

Funding Needed $86,000

Phase 3  - Interior Finishes

6%

FUNDS RAISED

Original Estimate $521,000

Funding Needed $490,000

Since the very beginning of Kingsway, God has faithfully provided for us and our families as we’ve trusted Him to lead the way. We continue recognizing that Kingsway is His school, and we are rejoicing in the many ways He has blessed us through faithful donors, volunteers, staff, and our school community. While there are financial needs for this project, we know that God has equipped each family with different talents, gifts, and resources. As we continue our journey with this capital campaign, we’re inviting you to join us on our journey...

Join our Journey - Donate Today!

Phase 1 - Sitework


We are excited to share that Phase 1 has been completed! Phase 1 was originally estimated at $300,000 but after significant donations-in-kind and cost savings, we are praising God that final expenditures came in at less than $110,000!  This phase included design and permitting, footers, foundations, underground utilities and the concrete floor slab.

Phase 1 Construction Now Complete!

Phase 2 - Exterior Structure


We have now moved into Phase 2 - Exterior Structure, originally estimated at $415,000. We are working to raise the remaining $86,000 and hope to complete Exterior Structure by December. This phase will include framing, roofing, siding, exterior veneers, exterior doors and windows.

Phase 2 Construction Now in Progress!

Phase 3 - Interior Finishes

This phase includes mechanical rough-ins, insulation, drywall, flooring, HVAC equipment, cabinets, etc. The beginning of the final phase of this project will take place this winter/spring while we work to raise the remaining $490,000 estimated for Phase 3. Pictured is a mock-up of the Eastside Classroom Building.

Thank You!


We are very grateful to everyone who has generously given to our Eastside Classroom Expansion Project.


A special thanks to Weaver Commercial Contractors for partnering with us on this project

and to the following businesses for their contributions.


Sugarcreek Concrete

Riceland Flowcare

Jay Yoder Concrete

Lincoln Way Construction, LLC


Contact Us

For more information on other giving options such as...


  • Make a pledge or one-time donation to our Capital Campaign
  • Make a direct donation from an IRA account (call for details)
  • Make a donation of appreciated stock or other assets (call for details)
  • Include Kingsway in your estate planning (call for details)


Checks may be made payable to Kingsway Christian School and mailed to 11138 Old Lincoln Way E, Orrville, Ohio 44667. Campaign should be noted in the memo section. A receipt will be provided for all donations. Thank you for giving to Kingsway, a 501(c)(3) organization.