2025-2026

Eastside Classroom

Expansion Progress update

In collaboration with Weaver Commercial Contractors, the Eastside Classroom Expansion Project began in June 2025. This building project is designed to add four new classrooms through the following phases by July 2026. However, we must raise the remaining estimated funds as indicated below. Any funds we receive beyond our construction costs will be used towards furnishing the new classrooms.

Funding Update

as of September 30, 2025

Phase 1 - Sitework

100%

Complete!

Original Estimate $300,000

Funding Needed $0

Phase 2 - Exterior Structure

72%

In progress

Original Estimate $415,000

Funding Needed $115,000

Phase 3 - Interior Finishes

0%

Coming soon

Original Estimate $521,000

Funding Needed $490,000

Since the very beginning of Kingsway, God has faithfully provided for us and our families as we’ve trusted Him to lead the way. We continue recognizing that Kingsway is His school, and we are rejoicing in the many ways He has blessed us through faithful donors, volunteers, staff, and our school community. While there are financial needs for this project, we know that God has equipped each family with different talents, gifts, and resources. As we continue our journey with this capital campaign, we’re inviting you to join us on our journey...

Join our Journey - Donate Today!

Eastside Building Dedication

Phase 1 - Sitework

We are excited to share that Phase 1 has been completed! Phase 1 was originally estimated at $300,000 but after significant donations-in-kind and cost savings, final expenditures came in at less than $110,000!  This phase includes design and permitting, footers, foundations, underground utilities and the concrete floor slab.

COMPLETE!

Phase 2 - Exterior Structure

We have now moved into Phase 2 - Exterior Structure, originally estimated at  $415,000. We have currently raised all but $115,000 and hope to complete Phase 2 by December. This phase will include framing, roofing, siding, exterior veneers, exterior doors and windows. Photos of our progress will be coming soon.

IN PROGRESS

Phase 3 - Interior Finishes

This phase includes interior finishes including; mechanical rough-ins, insulation, drywall, flooring, HVAC equipment, cabinets, etc. The beginning of the final phase of this project will take place this winter/spring while we work to raise the remaining $521,000 estimated for Phase 3. To the right is a mock-up of the Eastside Classroom Building.

COMING SOON...

Thank You!


We are very grateful to everyone who has generously given to our Eastside Classroom Expansion Project.


A special thanks to Weaver Commercial Contractors for partnering with us on this project.